Made-to-order cabinets from our Foshan factory - shipped duty-paid to the US, Canada & Australia +86 177 0868 3991

Collections

Kitchens Bath vanities Closets & wardrobes Mudroom & pantry Laundry rooms Home office Stainless steel Lacquered fronts Veneer & oak Oakline Flatstone Fluted

Projects

All projects

Solutions

How we work Cabinet options OEM / ODM Commercial & hospitality Dealers & wholesale

By market

United States Australia Africa Canada United Kingdom Saudi Arabia

By project

Apartments & multi-family Hotels & hospitality Villas & whole-home Importers & trade buyers

Company

About Factory & capacity Quality & warranty Blog

Guides

Importing & compliance Sourcing & QC Installation guide Contact Get a quote WhatsApp +86 177 0868 3991

Home / Blog / Sourcing & QC

Guide · Sourcing & QC

How long do custom cabinets take? A China factory schedule.

The committed numbers are 10-14 factory days for a kitchen or vanity run and 18-22 days of duty-paid transit to the US West Coast. This guide shows where those days go stage by stage - who controls each one, which can be compressed, and the one week of the calendar that moves every schedule made in China.

Assembler fitting cabinet panels during trial assembly in the factory assembly hall
The committed lead time is the sum of thirteen stages - and the stages overlap.

How long do custom cabinets take

How long do custom cabinets take? For a standard kitchen or vanity program, the factory commitment is 10-14 days of production counted from confirmed drawings, followed by 18-22 days of duty-paid ocean transit to the US West Coast or 32-40 days to the East Coast. Closet and wardrobe systems run 12-16 days in the factory. If the program needs a custom door profile or colour, add a 7-10 day sample stage before the drawings are frozen. In practice that puts most orders four to five weeks door to door to Vancouver or the US West, and six to eight weeks to the US East.

Those are the committed numbers, and they are published on the factory page. What the committed number does not show is where the days actually go - which desk holds each stage, which days belong to you rather than the factory, and which parts of the calendar no amount of planning can move. This article lays that out stage by stage, using the same schedule our own project managers work to.

Two clocks: the commitment and the internal schedule

A factory runs on two different clocks, and buyers who confuse them end up either suspicious or complacent. The first clock is the committed lead time: 10-14 days for kitchen and vanity runs, 12-16 for closet and wardrobe systems, with the production slot confirmed in writing before any deposit is taken. The second clock is the internal schedule - the day allowance each stage of the order carries while it moves through the plant. Stages overlap, some run in parallel, and the committed number is what falls out the other end on a standard run.

The internal schedule matters most on custom programs, where the work is larger and the stages are quoted per project. Below is that schedule, the one our custom department measures against once drawings are confirmed.

Inside the factory: the stage-by-stage schedule

Machining head inside a CNC centre boring system holes and hardware bores behind the guard
Cutting, banding and drilling each carry a 1-3 day allowance; on a standard run they run back-to-back.
StageDaysWhat happens
Order worksheet0.5Merchandiser turns the quote into a production order
Shop drawings1-5Engineering draws the confirmed design for your approval
Drawing review1A separate reviewer checks the drawings against the spec
Breakdown2-7Each panel is decomposed into cut lists and machine files
Material prep1-7Sheets pulled, graded and acclimatized; can start early when a job is urgent
Cutting1-3CNC sizing to the cut lists
Edge banding1-3Banding applied and end-trimmed
Drilling1-3System holes and hardware bores
Sorting1-3Panels matched to cabinets and rooms
Trial assembly3-7Every run assembled before packing
Inspection1Final QC, photos at 24, 48 and 72 hours during production
Packing2Crating, corner protection, palletising
Packing list and export filing2-3Documentation and export inspection filing

A few honest notes on that table. The 2-7 day allowance on breakdown is a ceiling our project managers chase hard - internal practice is to escalate any order still sitting there on day three. Material prep can be pulled ahead of breakdown when a schedule is tight, because board quantities can be estimated from the final drawings. And the export filing line hides the least predictable number in the whole chain: the inspection filing itself is 1-7 days, and in busy seasons it has stretched past ten. That stage belongs to the paperwork system, not to the factory floor, and no production plan can compress it.

On a standard kitchen run, the stages overlap and run back-to-back, which is how the committed 10-14 days holds. On a custom program - a hotel, a multi-unit dealer order, an OEM profile build - the same allowances are what the project manager schedules against, and the honest answer to how long do custom cabinets take at that scale is: it is quoted per project, with staged delivery available.

What moves the schedule - and who controls it

Cabinet door fronts strapped inside a wooden export crate with foam inserts and corner protection
Packing is a 2-day stage: crating, corner protection and palletising before the container seals.
SegmentControlled byWhat moves it
Shop drawings and approvalYouHow fast you review and approve; the allowance is 1-5 days
Sample stageShared7-10 days from sketch to a 1:1 sample on your bench
Production stagesFactorySlot booking, material prep pulled ahead of breakdown
Export documentationSharedInspection filing runs 1-7 days on the paperwork system
Ocean transitCarrierSailing schedules, port congestion, holiday peaks

The buyer-controlled rows are the ones worth staring at. A program that sits four days in drawing approval has pushed its own delivery by four days, and no factory promise was broken to cause it. The frozen-spec guide exists precisely because late spec changes are the most common self-inflicted delay: every change to board, colour, banding or hardware is a new version and a new approval cycle, not a quiet edit.

The ocean segment

White kitchen with a stone island delivered complete
Once sealed, the published DDP transit applies: 18-22 days to the US West Coast, 32-40 to the East.

Once the container seals, the published transit numbers apply as part of the DDP service: 18-22 days to the US West Coast and Vancouver, 32-40 days to the US East Coast, 15-20 days to Sydney. Those numbers carry the freight, import duties, customs clearance and drayage inside them. The tariff and border guide covers what happens at each border; the scheduling point is simpler - the sailing you get depends on when the container is sealed relative to the carrier's weekly schedule, which is why the packing and documentation stages above are run back-to-back with inspection rather than after it.

The calendar risk: Chinese New Year

One date moves every schedule made in China. Chinese New Year 2026 falls on 17 February, and 2027 on 6 February - the dates are published years ahead (timeanddate). The official public holiday is about a week, but the real gap is longer: most factories wind down in the week before, stay closed for two to three weeks as workers travel home, and take another one to two weeks to return to full output. Plan around an effective gap of roughly five weeks, not seven days (Wikipedia has the background on why the date moves each year).

Two second-order effects matter to importers. First, freight rates spike in the four weeks before the holiday as every factory races to ship, and space tightens with them - the Freightos index shows the pattern every year. Second, the post-holiday backlog stretches port handling, so a container that sails right after the holiday can sit longer at origin. The practical rule: confirm orders and lock production slots by early December, and treat any program that would sail in the first three weeks of February as a January decision.

How to protect your date

  • Get the production slot confirmed in writing before the deposit - it is the published policy, and it converts a promise into a schedule.
  • Freeze the spec before drawings start. Late changes restart the approval clock, not just the drawing.
  • Order samples in parallel with slot booking, not after. The 7-10 day sample stage only delays the program if it is run sequentially.
  • Plan the calendar around Chinese New Year if your delivery window lands in January or February.
  • Book your third-party inspection (SGS, Intertek or BV) when packing starts, so the inspector is on site the day the run is assembled - not a week later, with the container already sealed.

If you are working backwards from an opening date, the first 90 days guide walks the full timeline from first contact to a restocked container, and the MOQ guide explains how order size interacts with the schedule. For a program-specific answer to how long do custom cabinets take - hotel, multi-unit or OEM - send the drawings through the OEM / ODM page or contact us and the schedule comes back with the quote.

FAQ

How long do custom cabinets take from order to delivery?

Count 10-14 factory days for a kitchen or vanity run from confirmed drawings, then 18-22 days of duty-paid transit to the US West Coast or 32-40 to the East Coast. A custom profile or colour adds a 7-10 day sample stage before drawings are frozen.

How long is production after the drawings are approved?

10-14 days for kitchen and vanity programs, 12-16 days for closet and wardrobe systems. The production slot is confirmed in writing before any deposit is taken.

How long does ocean freight take?

Inside the DDP number: 18-22 days to the US West Coast and Vancouver, 32-40 days to the US East Coast, 15-20 days to Sydney. Freight, duties, clearance and drayage are included.

Does Chinese New Year affect cabinet lead times?

Yes. Factories wind down before the holiday, close for two to three weeks, and return to full output over another week or two. Confirm orders by early December if your container would sail in January or February.

How long does a sample take?

A 1:1 sample from your sketch, photo or a reference door ships in 7-10 days, and the sample stage carries no minimum. A painted sample of your actual colour ships with the first quote.

Can production be rushed?

Material prep can be pulled ahead of breakdown on urgent jobs, and parallel sample work saves a week. Trial assembly, inspection and the export filing cannot be compressed - the filing alone runs 1-7 days on the paperwork system.

Send the drawings, get the schedule back.

A floor plan or a confirmed set of shop drawings is enough to return a production slot and a door-to-door schedule, staged if the project needs it. OEM / ODM program terms · Contact page

Part of the sourcing and spec guide series - the full cluster, in reading order.